Power shortages hold back Mexico’s AI data centre push, Bloomberg reports

Mexico is struggling to draw AI data centres because its grid and permitting system lag, Bloomberg reported, holding 71 of Latin America's data centres against Brazil's 225. CloudHQ's top executive in Mexico said an electricity connection contract normally takes at least eight months and can take up to three years.