VTA Flags Rising Costs and Longer Timeline for South Bay BART Extension

VTA warns that the BART Silicon Valley Phase II extension will exceed its $12.7 billion cost estimate and take longer than projected, with completion now expected in 2037 and tunneling moved to early 2028. About $12 billion is secured, including a $5.1 billion federal pledge, but a funding gap remains and VTA is weighing options such as phasing the work.